Skatepark construction under way

We pleased to report that work is on schedule having started on Mon 27 Feb. After installation of security fencing, H&S requirements, receiving plant etc the Bendcrete installation team started work on removing the old steel skatepark on Tues 28 Feb. The old steel ramps had all been removed by mid-morning!. The preparation of the concrete binding material is now in place. This will be followed by installing steel copings and reinforcing mesh which will be hopefully in place next week, Please take a look at the Facebook album pics to see how it is all shaping up. The sprayed skatepark should take between 6 to 8 weeks, weather permitting.

More updates to follow next week on our Facebook page


Sign up to our Email Newsletter

Please enter your details below to receive our newsletter:

©2024 Horley Town Council. All rights reserved. Terms & Conditions | Privacy Notice
Website Design By J&L Digital